Finishing Works Progress at D1 Tower

Construction Week

“The structure including the roof fae steel skeleton of the building has been completed, whilst 92of the fae panel work has also been completed with the building effectively sealed to Level 74” says Kele Contracting project manager Colin Hindes.


Ground-level external podium works including the swimming pool and water feature structures are nearing completion which will allow completion of the podium floor glazing and installation of the feature timber canopy (due to commence late September). Mechanical, electrical, plumbing and fire services are essentially 80complete, while internal blockwork and plasterboard partitioning, painting, joinery and tiling works are well advanced on the upper floors of the development. All the plant rooms have been fitted-out with the machinery and equipment and are approaching final connections readying for initial testing.

 